November 21st: Work on the Caladium roofs began with the following steps:
1. Removal of the Sola Hot water panels
2. Removal and scraping of the shingles
3. Ensuring that the roof is free of rotten plywood and replaced when necessary
4. Thoroughly cleaning the surface
5. Application of the vapor barrier
6. Installation of the Galvalume steel
7. Reinstallation of the hot water panels

The roof repair and replacement project is ahead of schedule, the Caladium roof is complete after less than a week of labour. Work on the Croton roof is starting immediately.